20-18-C1: Sub-Basin S004 Sewer Main Realignment | Rogers Avenue
Contractor
Forsgren, Inc.
Designer/Engineer
Hawkins – Weir Engineers, Inc.
Estimated Completion Date
2/20/2023
Total Project Cost
$1,078,140.00
Scope of Work
This project will replace approximately 641 linear feet of 10-inch and 12-inch diameter pipe that runs along Rogers Ave., between Waldron Road and South 56th Street, with an 18-inch diameter pipe, including one service connection and five manholes. Also, the project will realign this section of pipe to be outside of the ArDOT HWY 22 right-of-way. The new pipe will be installed utilizing open-cut and horizontal-directional-drilling (HDD) methods.