21-22-C1: Basin 10 & 14 Capacity Improvements, Schedule 1
Contractor
McKee Utility Contractors, Inc.
Designer/Engineer
Hawkins – Weir Engineers, Inc.
Estimated Completion Date
5/06/2024
Total Project Cost
$12,824,091.00
Scope of Work
This project consists of installing approximately 3,514 linear feet of 42-inch diameter, 981 linear feet of 30-inch diameter, and 467 linear feet of 24-inch diameter sanitary sewer main, 26 manholes, and appurtenances.
The project area will include the west side of Martin Luther King Park to the south intersection of N L St and N 31st St.