20-18-C1: Sub-Basin S004 Sewer Main Realignment | Rogers Avenue

Contractor

Forsgren, Inc.

Designer/Engineer

Hawkins – Weir Engineers, Inc.

Estimated Completion Date

2/20/2023

Total Project Cost

$1,078,140.00

Scope of Work

This project will replace approximately 641 linear feet of 10-inch and 12-inch diameter pipe that runs along Rogers Ave., between Waldron Road and South 56th Street, with an 18-inch diameter pipe, including one service connection and five manholes. Also, the project will realign this section of pipe to be outside of the ArDOT HWY 22 right-of-way. The new pipe will be installed utilizing open-cut and horizontal-directional-drilling (HDD) methods.