19-26-C1: 2015 SSA Remedial Measures – Upsizing 6″ Sewer Mains

Contractor

Goodwin & Goodwin, Inc.

Designer/Engineer

Hawkins – Weir Engineers, Inc.

Estimated Completion Date

12/01/2022

Total Project Cost

$882,103.00

Scope of Work

This project completed the required remediation from the 2015 SSA work. It consists of replacing 6-inch pipes using open cut or pipe burst methods with 8-inch pipes. This project includes approximately 2,440 linear feet of pipe, 44 cleanouts, and 13 manholes.

A change order may be issued on this project which would increase the project cost and extend the estimated completion date.

Maps / Plans for Download